Vitreous LabsEnergy transparency

Ristimäki (Olana Energy)

Being built, 30 MW · 34 MWh, in Pieksämäki, owned by Olana Energy Oy. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power30 MW
Capacity34 MWh
Duration1.1 hours
StatusBeing built, as of 11 October 2026
Owner’s date2026 Q4, expected
MunicipalityPieksämäki
Grid connectionFingrid transmission grid
Placed on the mapat Ristimäki, the place its name carries (GeoNames)

Who is behind it

OwnerOlana Energy Oy
DeveloperOlana Energy
Business ID3376259-7

YTJ, by exact name: Olana Energy Oy. https://avoindata.prh.fi/opendata-ytj-api/v3/companies?businessId=3376259-7

Not published anywhere we have found: ultimate owner, built by, cells. The page says so rather than guessing.

What the sources say

Olana (7 Oct 2026): entering commissioning "during the coming months". Its March 2026 post had given Q3/2026.

Evidence and sources

From the owners’, developers’ and builders’ own releases, council decisions and permit bulletins, read by Vitreous and checked against the owners’ own words on 12 October 2026; a bracket such as “(Energy-Storage.news only)” in a field means the trade press is still the only source for it. Fingrid publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Fingrid’s markets is on the markets page, for the whole market and never for a named battery. List id FI-B036.