Vitreous LabsEnergy transparency
Belgium · the batteries

Auvelais Energy Storage

Being built, 76 MW · 304 MWh, in Sambreville, owned by Energy Solutions Group. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power76 MW
Capacity304 MWh
Duration4.0 hours
StatusBeing built, as of 19 October 2026
Owner’s date2027, expected in the first quarter of 2027
MunicipalitySambreville, Auvelais, Namur
Grid connectionElia 150 kV, a substation on the site
Placed on the mapat Auvelais, the place its source names, in Sambreville (GeoNames)

Who is behind it

OwnerEnergy Solutions Group
Ultimate ownerPatronale Life (majority)
Traded byCentrica Energy
Built byTesla (82 Megapack 2XL); SPIE

Not published anywhere we have found: developer. The page says so rather than guessing.

Not in Elia’s list

Elia does not schedule this battery, because it is not yet running.