Vitreous LabsEnergy transparency
Belgium · the batteries

EStor-Lux I

Operating, 10 MW · 20 MWh, in Bastogne, owned by EStor-Lux consortium (SRIW, Ackermans & van Haaren, BEWATT, SOCOFE, SOFILUX). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power10 MW
Capacity20 MWh
Duration2.0 hours
StatusOperating, as of 19 October 2026
Owner’s dateDecember 2021, actual, in the frequency reserve market
MunicipalityBastogne, Luxembourg province
Grid connectionElia
Placed on the mapat the centre of Bastogne, its municipality (GeoNames)

Who is behind it

OwnerEStor-Lux consortium (SRIW, Ackermans & van Haaren, BEWATT, SOCOFE, SOFILUX)
Traded byCentrica Business Solutions
Built byFluence

Not published anywhere we have found: ultimate owner, developer. The page says so rather than guessing.

In Elia’s list

Elia schedules this battery under the name below. Elia usually starts scheduling a battery when it begins testing, so the first day here is when it reached the grid, not when it began commercial operation.

Elia’s nameFirst listedLast listedPower, as Elia lists it
Estor-Lux _ Storage23 October 2024still listed12 MW from 23 October 2024

Elia Transmission Belgium, open data dataset ods179, Elia Open Data Licence.

What the sources say

Elia lists 11.5 MW. Developed by BSTOR; the investors named at the inauguration in April 2022 are those above, with CFE and IDELUX also involved. In the Belgian province of Luxembourg, not the Grand Duchy.

Evidence and sources

From the owners’, developers’ and builders’ own releases and the trade press, read by Vitreous, joined to Elia’s list by name. This page carries no money: no Belgian body publishes what a named battery earns. List id BE-B05.

All batteries  ·  On the map