Navagne (Luminus Storage Visé)
Operating, 150 MW · 600 MWh, in Visé, owned by Luminus (EDF group) with I4B. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 150 MW |
| Capacity | 600 MWh |
| Duration | 4.0 hours |
| Status | Operating, as of 19 October 2026 |
| Owner’s date | 1 September 2026, actual, inaugurated |
| Municipality | Visé, Lixhe, Liège |
| Grid connection | Elia, high voltage |
| Placed on the map | at the site itself, as mapped on OpenStreetMap (Parc de batteries électriques Luminus) |
Who is behind it
| Owner | Luminus (EDF group) with I4B |
| Traded by | Luminus |
| Built by | Luminus (integrator); 132 containers |
Not published anywhere we have found: ultimate owner, developer. The page says so rather than guessing.
In Elia’s list
Elia schedules this battery under the name below. Elia usually starts scheduling a battery when it begins testing, so the first day here is when it reached the grid, not when it began commercial operation.
| Elia’s name | First listed | Last listed | Power, as Elia lists it |
|---|---|---|---|
| Luminus Storage Visé BESS | 7 February 2026 | still listed | 150 MW from 7 February 2026 |
Elia Transmission Belgium, open data dataset ods179, Elia Open Data Licence.
Navagne (Luminus Storage Visé) made 0.1 full discharges a day over the last 30 days of the meter
ENTSO-E publishes this battery’s metered output, hour by hour. A full discharge is its output divided by the 600 MWh its owner states it holds.
Navagne (Luminus Storage Visé)
150 MW · 600 MWh · first output 27 February 2026
| Month | MWh out | Full discharges | |
|---|---|---|---|
| February 2026 | 5.34 | 0.0 | part month |
| March 2026 | 53 | 0.1 | |
| April 2026 | 2,045 | 3.4 | |
| May 2026 | 3,081 | 5.1 | |
| June 2026 | 7,434 | 12.4 | |
| July 2026 | 8,763 | 14.6 | |
| August 2026 | 9,070 | 15.1 | |
| September 2026 | 6,669 | 11.1 | |
| October 2026 | 2,544 | 4.2 | part month |
ENTSO-E Transparency Platform, actual generation per generation unit (16.1.A), units BESS Navagne, read 20 October 2026. Output only: ENTSO-E publishes no charging per unit.
What the sources say
Elia lists it from February 2026, during testing. ENTSO-E publishes its output as BESS Navagne.
Evidence and sources
- owner: ess-news.com/2026/09/04/edf-brings-e160-million-600-mwh-nava…
- status: energy-storage.news/belgium-edf-inaugurates-600mwh-bess-engie-start…
- more: energynews.pro/edf-power-solutions-inaugurates-a-150-mw-batter…
- position: openstreetmap.org/way/199898160