Vitreous LabsEnergy transparency
Belgium · the batteries

Ruien II

Being built, 100 MW · 250 MWh, in Kluisbergen, owned by Nippon Koei Energy Europe (51%), Aspiravi (24.5%), Ecopower (19.6%), Beauvent (4.9%). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power100 MW
Capacity250 MWh
Duration2.5 hours
StatusBeing built, as of 19 October 2026
Owner’s date2027, expected in autumn 2027
MunicipalityKluisbergen, Ruien, East Flanders
Grid connectionElia, Ruien 150 kV
Placed on the mapat Ruien, the place its source names, in Kluisbergen (GeoNames)

Who is behind it

OwnerNippon Koei Energy Europe (51%), Aspiravi (24.5%), Ecopower (19.6%), Beauvent (4.9%)

Not published anywhere we have found: ultimate owner, developer, traded by, built by. The page says so rather than guessing.

Not in Elia’s list

Elia does not schedule this battery, because it is not yet running.

What the sources say

Two parts, 74.9 MW and 149.8 MWh, and 25.1 MW and 100.4 MWh. The second part’s 25.1 MW is the same as the first Ruien battery’s figure in Elia’s list, by coincidence. Construction began on 2 April 2026; the first spade was turned on 6 May 2026.

Evidence and sources

From the owners’, developers’ and builders’ own releases and the trade press, read by Vitreous, joined to Elia’s list by name. This page carries no money: no Belgian body publishes what a named battery earns. List id BE-B23.