Belgium · the batteries
Storm Langerlo
Being built, 100 MW · 400 MWh, in Genk, owned by Storm. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 100 MW |
| Capacity | 400 MWh |
| Duration | 4.0 hours |
| Status | Being built, as of 19 October 2026 |
| Owner’s date | 2027, expected in the second half of 2027 |
| Municipality | Genk, Langerlo, Limburg |
| Grid connection | Elia, André Dumont substation |
| Placed on the map | at the site itself, as mapped on OpenStreetMap (Batterijpark Storm - Langerlo) |
Who is behind it
| Owner | Storm |
| Ultimate owner | with TINC, PMV and I4B |
| Traded by | Eneco |
| Built by | Tesla |
Not published anywhere we have found: developer. The page says so rather than guessing.
Not in Elia’s list
Elia does not schedule this battery, because it is not yet running.
What the sources say
Elia’s connection was built by March 2026. The sources give dates from early to the end of 2027 for the start.
Evidence and sources
- owner: vfb.be/Media/Default/pdf/TINC_Persbericht_Volt_NL.pdf
- size: vrt.be/vrtnws/nl/2026/03/25/batterijpark-langerlo-genk…
- more: vrt.be/vrtnws/nl/2025/12/10/hoogspanningsnetbeheerder-…
- position: openstreetmap.org/way/1457465135
From the owners’, developers’ and builders’ own releases and the trade press, read by Vitreous, joined to Elia’s list by name. This page carries no money: no Belgian body publishes what a named battery earns. List id BE-B22.