Vitreous LabsEnergy transparency
The Netherlands · the named batteries

Attero Tilburg

Investment decided, not yet being built, 9 MW · 18 MWh, in Tilburg, owned by Attero. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power9 MW
Capacity18 MWh
Duration2.0 hours
StatusInvestment decided, not yet being built, as of 20 October 2026
Stated date2026, expected in the second half of 2026
MunicipalityTilburg, Noord-Brabant
Placed on the mapat the centre of Tilburg, its municipality (GeoNames)
How sureProbable: the sources agree but none confirms every fact

Who is behind it

OwnerAttero

Not published anywhere we have found: traded by, built by.

What the sources say

The investment is announced; no source says building has begun.

Evidence and sources

From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B63.

All batteries  ·  On the map