Begro Noordoostpolder (Westermeerdijk)
Announced, 180 MW · 720 MWh, in Noordoostpolder, owned by Begro Energy Projects. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 180 MW |
| Capacity | 720 MWh |
| Duration | 4.0 hours |
| Status | Announced, as of 20 October 2026 |
| Stated date | 2025, first phase planned mid-2025, full 2026 (stated Dec 2023) |
| Municipality | Noordoostpolder, Flevoland |
| Grid connection | TenneT; TenneT Westermeerdijk |
| Placed on the map | at the centre of Noordoostpolder, its municipality (GeoNames) |
| How sure | Probable: the sources agree but none confirms every fact |
Who is behind it
| Owner | Begro Energy Projects |
| Built by | Ventolines (development) |
Not published anywhere we have found: traded by.
What the sources say
Planned dates have passed with no build confirmation. New Project Media reports Begro marketing a 400 MW-plus portfolio (headline only).; Conflict: 250 MW / 1,000 MWh (December 2023, January 2024) against 180 MW / 720 MWh in Begro's sale portfolio (New Project Media, after December 2024; the article describes the wider project as up to 250 MW). The later figure is used. Zoning plan irrevocable December 2024; environmental permits were expected in H2 2025 and are not confirmed, so status is planned.
Evidence and sources
- source: solarmagazine.nl/nieuws-zonne-energie/i36148/noordoostpolder-kri…
- source: energy-storage.news/dutch-municipality-backs-250mw-1000mwh-bess
- source: newprojectmedia.com/netherlands-begro-approaches-market-with-400-mw…
From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B43.