Vitreous LabsEnergy transparency
The Netherlands · the named batteries

Enecogen battery (Rotterdam port)

Investment decided, not yet being built, 50 MW · 200 MWh, in Rotterdam, owned by Eneco and EP NL (50/50). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power50 MW
Capacity200 MWh
Duration4.0 hours
StatusInvestment decided, not yet being built, as of 20 October 2026
Stated date2027
MunicipalityRotterdam, port, Enecogen site, Zuid-Holland
Grid connectionexisting Enecogen power plant connection
Placed on the mapat the centre of Rotterdam, its municipality (GeoNames)
How sureProbable: the sources agree but none confirms every fact

Who is behind it

OwnerEneco and EP NL (50/50)
Traded byEneco and EP NL trading desks; Enecogen O&M

Not published anywhere we have found: built by.

What the sources say

Construction start not confirmed.

Evidence and sources

From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B36.

All batteries  ·  On the map