Vitreous LabsEnergy transparency
The Netherlands · the named batteries

Greenchoice battery relocated to Hellegatsplein

Built or due, running not confirmed, 10 MW · 10 MWh, in Hellegatsplein wind park, owned by Greenchoice. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power10 MW
Capacity10 MWh
Duration1.0 hours
StatusBuilt or due, running not confirmed, as of 20 October 2026
Stated date2018, originally 2018/2019 at Hartelkanaal; relocated 2025
MunicipalityHellegatsplein wind park, Zuid-Holland
Placed on the mapnot placed: Hellegatsplein wind park is not in GeoNames
How surePossible: a single or old source, not confirmed since

Who is behind it

OwnerGreenchoice
Traded byGreenchoice
Built byAlfen

What the sources say

Same asset as the 2019 Hartelkanaal 10 MWh battery, the ESN 2019 '10MW battery near Rotterdam' story and Alfen's 2019 Port of Rotterdam 10 MW / 10 MWh award. Recommissioning at Hellegatsplein not explicitly confirmed. Province inferred.; Status set to construction: the April 2025 relocation is confirmed, recommissioning at Hellegatsplein is not. Possible. Alfen finished moving the battery to Hellegatsplein by March 2025; no source says it is running.

Evidence and sources

From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B24.