Vitreous LabsEnergy transparency
The Netherlands · the named batteries

Greenchoice Hartel 2 battery

Operating, 20 MW · 40 MWh, in Rotterdam, owned by Greenchoice (financed by Triodos; ownership not stated explicitly). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power20 MW
Capacity40 MWh
Duration2.0 hours
StatusOperating, as of 20 October 2026
Stated dateMarch 2025, delivered and in use
MunicipalityRotterdam, Hartelkanaal wind park, Zuid-Holland
Placed on the mapat the centre of Rotterdam, its municipality (GeoNames)
How sureA dated source confirms it

Who is behind it

OwnerGreenchoice (financed by Triodos; ownership not stated explicitly)
Traded byGreenchoice
Built byAlfen (EPC); Green Energy Storage (developer); Spectral (IT integration)

What the sources say

Replaced the 2019 10 MW battery at the same site, which was moved to Hellegatsplein (see next row).

Evidence and sources

From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B13.

All batteries  ·  On the map