The Netherlands · the named batteries
NOP Agrowind battery (NOP AgroBESS)
Investment decided, not yet being built, 49 MW · 196 MWh, in near Espel, owned by NOP Agrowind (not stated explicitly). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 49 MW |
| Capacity | 196 MWh |
| Duration | 4.0 hours |
| Status | Investment decided, not yet being built, as of 20 October 2026 |
| Stated date | 2026, Q4 2026 (installation from spring 2026) |
| Municipality | near Espel, Noordoostpolder, Flevoland |
| Grid connection | medium voltage via Alfen-built substation, integrated with the 195 MW NOP Agrowind wind farm |
| Placed on the map | at the site itself, as mapped on OpenStreetMap (Batterijopslag NOP AgroBESS) |
| How sure | Probable: the sources agree but none confirms every fact |
Who is behind it
| Owner | NOP Agrowind (not stated explicitly) |
| Built by | Alfen; Ventolines (integration) |
Not published anywhere we have found: traded by.
What the sources say
Supply contract only. No source confirms installation has begun. This is NOT the Begro 250 MW / 1 GWh Westermeerdijk project, though Ventolines is on both.
Evidence and sources
- source: alfen.com/en/news/alfen-to-deliver-196mwh-battery-project…
- source: ventolines.nl/en/project_category/energy-storage-projects
- position: openstreetmap.org/way/1460547072
From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B37.