Sellingen floating solar park battery
Built or due, running not confirmed, 15 MW · 30 MWh, in Sellingen, owned by (not stated) GroenLeven is the developer. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 15 MW |
| Capacity | 30 MWh |
| Duration | 2.0 hours |
| Status | Built or due, running not confirmed, as of 20 October 2026 |
| Stated date | 2023, planned end 2023 |
| Municipality | Sellingen, Westerwolde, Groningen |
| Grid connection | shared with the 41.4 MW floating solar park |
| Placed on the map | at the site itself, as mapped on OpenStreetMap (Batterijopslag Sellingen) |
| How sure | Possible: a single or old source, not confirmed since |
Who is behind it
| Owner | (not stated) GroenLeven is the developer |
Not published anywhere we have found: traded by, built by.
What the sources say
Being installed in July 2023 for operation by end 2023. A GroenLeven presentation (13 February 2024) shows it as an existing project and names Westerwolde, but no dated source says it runs, so status stays construction. Probably running. New in this round. GroenLeven placed the batteries beside the park in 2023; no source confirms they are running.
Evidence and sources
- source: solarmagazine.nl/nieuws-zonne-energie/i34852/groenleven-plaatst-…
- source: d66.nl/dronten/wp-content/uploads/sites/218/2024/02/1-…
- position: openstreetmap.org/way/1339033795
From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B48.