Announced, 320 MW · 640 MWh, in Zuidwending, owned by SemperPower (now Return) and Corre Energy. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power320 MW
Capacity640 MWh
Duration2.0 hours
StatusAnnounced, as of 20 October 2026
MunicipalityZuidwending, Veendam, Groningen
Placed on the mapat Veendam, the place its source names, in Zuidwending (GeoNames)
How surePossible: a single or old source, not confirmed since

Who is behind it

OwnerSemperPower (now Return) and Corre Energy

Not published anywhere we have found: traded by, built by.

What the sources say

Site is Corre Energy's Zuidwending CAES site (NS Energy, 8 July 2024). Veendam as municipality is my placement of Zuidwending. FID was targeted for late 2025 and COD 2026; nothing since. Not on Return's locations page (read 20 October 2026). Possible.

Evidence and sources

From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B44.

All batteries  ·  On the map