Strekdammen battery (Eemshaven)
Investment decided, not yet being built, 7.5 MW · 24 MWh, in Eemshaven, owned by a.s.r. Dutch Green Energy Fund I (majority); Rebel Development; Pronewable. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 7.5 MW |
| Capacity | 24 MWh |
| Duration | 3.2 hours |
| Status | Investment decided, not yet being built, as of 20 October 2026 |
| Stated date | February 2027, planned February 2027 |
| Municipality | Eemshaven, Het Hogeland, Groningen |
| Grid connection | via Strekdammen wind park |
| Placed on the map | at Eemshaven, the place its source names (GeoNames) |
| How sure | Probable: the sources agree but none confirms every fact |
Who is behind it
| Owner | a.s.r. Dutch Green Energy Fund I (majority); Rebel Development; Pronewable |
| Traded by | Rebel / Pronewable (involved in operation) |
Not published anywhere we have found: built by.
What the sources say
Construction was due to start in Feb 2026 according to an article from that month. Start not independently confirmed.; Status set to fid: a.s.r. bought the project (20 February 2026) with construction due to start that month; no source confirms work began. Probable.
Evidence and sources
From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B32.