Announced, 150 MW, in near Meeden, owned by Vopak. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power150 MW
StatusAnnounced, as of 20 October 2026
Stated date2028, contract start Q2 2028
Municipalitynear Meeden, Midden-Groningen, Groningen
Placed on the mapat Meeden, the place its source names (GeoNames)
How sureProbable: the sources agree but none confirms every fact

Who is behind it

OwnerVopak
Traded byVattenfall (tolls 100 MW / 400 MWh)

Not published anywhere we have found: built by.

What the sources say

4-hour duration would mean about 600 MWh, but no source states the total. Possible duplicate: Vopak bought a 300 MW ready-to-build northern-NL project from BayWa r.e./GroenLeven (21 May 2025/23). This may be part of it. Not confirmed.