Windpark Greenport Venlo battery
Investment decided, not yet being built, 15 MW · 60 MWh, in Venlo, owned by WGV-EOS (Greenchoice, ABN AMRO’s impact fund and Windunie). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 15 MW |
| Capacity | 60 MWh |
| Duration | 4.0 hours |
| Status | Investment decided, not yet being built, as of 20 October 2026 |
| Stated date | 2027, summer 2027 |
| Municipality | Venlo, Trade Port West, Greenport Venlo, Limburg |
| Placed on the map | at the centre of Venlo, its municipality (GeoNames) |
| How sure | Probable: the sources agree but none confirms every fact |
Who is behind it
| Owner | WGV-EOS (Greenchoice, ABN AMRO’s impact fund and Windunie) |
| Traded by | Greenchoice (control); GES (asset management) |
| Built by | Alfen (hardware); Green Energy Storage (realisation) |
What the sources say
Merged with the GES 25 MW / 50 MWh Venlo permit (25 November 2024): both are a GES battery for Windpark Greenport Venlo with Greenchoice, Windunie and ABN AMRO. Conflict: 25 MW / 50 MWh in the 2024 permit against 15 MW / 60 MWh at financial close (10 September 2026); the latest figure is used. The merge is my judgement from the shared wind park and partners; check. Probable. One project, redesigned from 25 MW and 50 MWh in the 2024 permit to 15 MW and 60 MWh; the Trade Port West location is from the 2024 permit.
Evidence and sources
- source: solarmagazine.nl/nieuws-zonne-energie/i44730/greenchoice-abn-amr…
- source: solarmagazine.nl/nieuws-zonne-energie/i39115/vergunning-green-en…