NWJ MET 3_GAILLON

A battery of 1.24 MW and 2.43 MWh in Gaillon, on Enedis’s distribution grid, in service since 7 January 2025. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.24 MW
Energy2.43 MWh
Hours at full power2.0
Charging power1.24 MW
In service7 January 2025
CommuneGaillon, Eure, Normandie
NetworkEnedis, HTA
Substation it connects throughGaillon (GAIL6)
Placed on the mapat the distribution substation it connects through (Gaillon), from Caparéseau
EIC code17W000002175735Y

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.