Vitreous LabsEnergy transparency

NWJ MET ANDEL II

A battery of 1.25 MW and 0.78 MWh in Andel, on Enedis’s distribution grid, in service since 31 May 2023. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.25 MW
Energy0.78 MWh
Hours at full power0.6
Charging power1.25 MW
In service31 May 2023
CommuneAndel, Côtes-d'Armor, Bretagne
NetworkEnedis, HTA
Substation it connects throughLamballe (LAMBA)
Placed on the mapat the distribution substation it connects through (Lamballe), from Caparéseau
EIC code17W000001554572X

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.

All batteries  ·  On the map