Vitreous LabsEnergy transparency

NWJ MET BAUD-SiteProductionMorale

A battery of 1.25 MW and 1 MWh in Baud, on Enedis’s distribution grid, in service since 3 September 2021. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.25 MW
Energy1 MWh
Hours at full power0.8
Charging power1.25 MW
In service3 September 2021
CommuneBaud, Morbihan, Bretagne
NetworkEnedis, HTA
Substation it connects throughBAUD
Placed on the mapat the centre of its commune, Baud, from geo.api.gouv.fr
EIC code17W000001321968I

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.