Vitreous LabsEnergy transparency

NWJ MET Bricqueville-la-Blouette

A battery of 1.24 MW and 2.43 MWh in Bricqueville-la-Blouette, on Enedis’s distribution grid, in service since 24 November 2025. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.24 MW
Energy2.43 MWh
Hours at full power2.0
Charging power1.24 MW
In service24 November 2025
CommuneBricqueville-la-Blouette, Manche, Normandie
NetworkEnedis, HTA
Substation it connects throughCoutances (COUTA)
Placed on the mapat the distribution substation it connects through (Coutances), from Caparéseau
EIC code17W000002378141Y

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.

All batteries  ·  On the map