A battery of 1.57 MW and 0 MWh in Buzet-sur-Tarn, on Enedis’s distribution grid, in service since 12 April 2022. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.57 MW
Energy0 MWh
Hours at full power0.0
Charging power1.25 MW
In service12 April 2022
CommuneBuzet-sur-Tarn, Haute-Garonne, Occitanie
NetworkEnedis, HTA
Substation it connects throughSt-Sulpice (SSSUL)
Placed on the mapat the distribution substation it connects through (St-Sulpice), from Caparéseau
EIC code17W000001383895A

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.