A battery of 1.24 MW and 2.46 MWh in Éragny-sur-Epte, on Enedis’s distribution grid, in service since 27 August 2024. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.24 MW
Energy2.46 MWh
Hours at full power2.0
Charging power1.24 MW
In service27 August 2024
CommuneÉragny-sur-Epte, Oise, Hauts-de-France
NetworkEnedis, HTA
Substation it connects throughTrie-Chateau (T.CH5)
Placed on the mapat the distribution substation it connects through (Trie-Chateau), from Caparéseau
EIC code17W0000020658429

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.