A battery of 1.24 MW and 2.43 MWh in Morgny-la-Pommeraye, on Enedis’s distribution grid, in service since 30 October 2025. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.
In the national register
| Power | 1.24 MW |
| Energy | 2.43 MWh |
| Hours at full power | 2.0 |
| Charging power | 1.24 MW |
| In service | 30 October 2025 |
| Commune | Morgny-la-Pommeraye, Seine-Maritime, Normandie |
| Network | Enedis, HTA |
| Substation it connects through | Cazerie (CAZE5) |
| Placed on the map | at the distribution substation it connects through (Cazerie), from Caparéseau |
| EIC code | 17W000002363944R |
What is not published
Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.
Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.