NWJ MET PLUZUNET
A battery of 1.57 MW and 0.78 MWh in Pluzunet, on Enedis’s distribution grid, in service since 4 October 2022. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.
In the national register
| Power | 1.57 MW |
| Energy | 0.78 MWh |
| Hours at full power | 0.5 |
| Charging power | 1.25 MW |
| In service | 4 October 2022 |
| Commune | Pluzunet, Côtes-d'Armor, Bretagne |
| Network | Enedis, HTA |
| Substation it connects through | Pluzunet (PLUZU) |
| Placed on the map | at the distribution substation it connects through (Pluzunet), from Caparéseau |
| EIC code | 17W000001436312V |
What is not published
Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.
Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.