NWJ MET POMMARD

A battery of 1.24 MW and 2.43 MWh in Pommard, on Enedis’s distribution grid, in service since 5 May 2025. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.24 MW
Energy2.43 MWh
Hours at full power2.0
Charging power1.24 MW
In service5 May 2025
CommunePommard, Côte-d'Or, Bourgogne-Franche-Comté
NetworkEnedis, HTA
Substation it connects throughMontagny (Les Beaune) (MTAGN)
Placed on the mapat the distribution substation it connects through (Montagny (Les Beaune)), from Caparéseau
EIC code17W0000022673409

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.