Vitreous LabsEnergy transparency

NWJ MET PONS

A battery of 1.1 MW and 0 MWh in Pons, on Enedis’s distribution grid, in service since 10 March 2020. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.1 MW
Energy0 MWh
Hours at full power0.0
Charging power1.1 MW
In service10 March 2020
CommunePons, Charente-Maritime, Nouvelle-Aquitaine
NetworkEnedis, HTA
Substation it connects throughPONS
Placed on the mapat the centre of its commune, Pons, from geo.api.gouv.fr
EIC code17W0000009631218

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.