A battery of 1.16 MW and 0.78 MWh in Sérézin-de-la-Tour, on Enedis’s distribution grid, in service since 28 November 2025. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.16 MW
Energy0.78 MWh
Hours at full power0.7
Charging power1.25 MW
In service28 November 2025
CommuneSérézin-de-la-Tour, Isère, Auvergne-Rhône-Alpes
NetworkEnedis, HTA
Substation it connects throughLa Tour-Du-Pin (T.PIN)
Placed on the mapat the distribution substation it connects through (La Tour-Du-Pin), from Caparéseau
EIC code17W000002376932D

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.