Vitreous LabsEnergy transparency

NWJ MET SIMARD

A battery of 1.24 MW and 2.43 MWh in Simard, on Enedis’s distribution grid, in service since 2 April 2026. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.24 MW
Energy2.43 MWh
Hours at full power2.0
Charging power1.24 MW
In service2 April 2026
CommuneSimard, Saône-et-Loire, Bourgogne-Franche-Comté
NetworkEnedis, HTA
Substation it connects throughChamp-Fournier (C.FOU)
Placed on the mapat the distribution substation it connects through (Champ-Fournier), from Caparéseau
EIC code17W000002456429R

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.

All batteries  ·  On the map