Vitreous LabsEnergy transparency

NWJ MET Tousson II

A battery of 1.24 MW and 2.43 MWh in Tousson, on Enedis’s distribution grid, in service since 26 February 2026. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.24 MW
Energy2.43 MWh
Hours at full power2.0
In service26 February 2026
CommuneTousson, Seine-et-Marne, Île-de-France
NetworkEnedis, HTA
Substation it connects throughTousson (TOUSS)
Placed on the mapat the distribution substation it connects through (Tousson), from Caparéseau
EIC code17W000002433167L

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.