SDC YDEAL CONFLUENCE
A battery of 0.05 MW and 0.2 MWh in Lyon 2e Arrondissement, on Enedis’s distribution grid, in service since 6 October 2022. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.
In the national register
| Power | 0.05 MW |
| Energy | 0.2 MWh |
| Hours at full power | 4.0 |
| Charging power | 0.05 MW |
| In service | 6 October 2022 |
| Commune | Lyon 2e Arrondissement, Rhône, Auvergne-Rhône-Alpes |
| Network | Enedis, BT |
| Substation it connects through | Perrache (PERRA) |
| Placed on the map | at the distribution substation it connects through (Perrache), from Caparéseau |
| EIC code | 17W0000014362599 |
What is not published
Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.
Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.