Storage site at Grandpuits

A battery of 43 MW and 43 MWh in Grandpuits-Bailly-Carrois, on RTE’s transmission grid, in service since 21 April 2023. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power43 MW
Energy43 MWh
Hours at full power1.0
Charging power43 MW
In service21 April 2023
CommuneGrandpuits-Bailly-Carrois, Seine-et-Marne, Île-de-France
NetworkRTE, 63 kV
Substation it connects throughGRAN7
Placed on the mapat the centre of its commune, Grandpuits-Bailly-Carrois, from geo.api.gouv.fr
EIC code17W000001600747U
Name as filedGRAN7S01-STOCKAGE N0 01 DE GRANDPUITS

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.