A battery of 20 MW and 16 MWh in Calce, on RTE’s transmission grid, in service since 1 December 2022. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power20 MW
Energy16 MWh
Hours at full power0.8
In service1 December 2022
CommuneCalce, Pyrénées-Orientales, Occitanie
NetworkRTE, 225 kV
Substation it connects throughP.RI5
Placed on the mapat the centre of its commune, Calce, from geo.api.gouv.fr
EIC code17W000001995366G
Name as filedP.RI5S01-STOCKAGE N0 01 DE PEZILLA-LA-RIVIERE

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.