A battery of 1.24 MW and 1.79 MWh in Villard-Bonnot, on GreenAlp’s distribution grid, in service since 23 November 2021. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power1.24 MW
Energy1.79 MWh
Hours at full power1.4
Charging power1.24 MW
In service23 November 2021
CommuneVillard-Bonnot, Isère, Auvergne-Rhône-Alpes
NetworkGreenAlp, HTA
Substation it connects throughFroges (FROGE)
Placed on the mapat the distribution substation it connects through (Froges), from Caparéseau
EIC code17W000001352408X

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.