A battery of 2.5 MW and 2.5 MWh in Gièvres, on Enedis’s distribution grid, in service since 7 February 2023. Every fact below is the national register’s own, and a field not shown is one the register leaves blank.

In the national register

Power2.5 MW
Energy2.5 MWh
Hours at full power1.0
Charging power2.5 MW
In service7 February 2023
CommuneGièvres, Loir-et-Cher, Centre-Val de Loire
NetworkEnedis, HTA
Substation it connects throughSelles-Sur-Cher (S.CHE)
Placed on the mapat the distribution substation it connects through (Selles-Sur-Cher), from Caparéseau
EIC code17W000001469875S

What is not published

Who owns this battery, who trades its power, and what it earns: the register carries none of these, and no French body publishes a battery’s metered output or the instructions RTE gives it.

Source: Registre national des installations de production et de stockage d’électricité, register of 31 August 2026, on ODRÉ, Licence Ouverte 2.0. Substation positions from Caparéseau.