Aunslev solar park battery

Announced, 8.4 MW · 17 MWh, in Nyborg Municipality, owned by Aunslev Solcellepark ApS. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power8.4 MW
Capacity17 MWh
Duration2.0 hours
StatusAnnounced, as of 24 June 2026
Bidding zoneDK1, West Denmark
MunicipalityNyborg
Placed on the mapat the centre of Nyborg Municipality (GeoNames)
Nearest transmission stationFraugde (150 kV), 15 km away: 69 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026

Who is behind it

OwnerAunslev Solcellepark ApS

Not published anywhere we have found: ultimate owner, developer, built by, optimiser.

What the sources say

Screening decisions of 12 and 24 June 2026, Nederbyvej.

Evidence and sources

From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B056.