Announced, 8.4 MW · 17 MWh, in Nyborg Municipality, owned by Aunslev Solcellepark ApS. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 8.4 MW |
| Capacity | 17 MWh |
| Duration | 2.0 hours |
| Status | Announced, as of 24 June 2026 |
| Bidding zone | DK1, West Denmark |
| Municipality | Nyborg |
| Placed on the map | at the centre of Nyborg Municipality (GeoNames) |
| Nearest transmission station | Fraugde (150 kV), 15 km away: 69 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | Aunslev Solcellepark ApS |
Not published anywhere we have found: ultimate owner, developer, built by, optimiser.
What the sources say
Screening decisions of 12 and 24 June 2026, Nederbyvej.
Evidence and sources
- name: nyborg.dk/media/n2ohyszb/afgoerelse-om-at-etablering-af-b…
- power: nyborg.dk/media/pwtfdpjl/d2026-135781_afgc3b8relse_om_ikk…
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B056.