Borup battery, Skævinge
Being built, 5 MW · 10 MWh, in Hillerød Municipality, owned by Nordic Solar. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 5 MW |
| Capacity | 10 MWh |
| Duration | 2.0 hours |
| Status | Being built, as of 14 April 2025 |
| Owner’s date | Q1 2025, expected |
| Bidding zone | DK2, East Denmark |
| Municipality | Hillerød |
| Placed on the map | at Skævinge, the place its source names (GeoNames) |
| Nearest transmission station | Borup (132 kV), 2 km away: 696 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | Nordic Solar |
| Developer | Nordic Solar |
Not published anywhere we have found: ultimate owner, built by, optimiser.
What the sources say
Green Power Denmark reported it under construction on 14 April 2025; completion had been expected by the end of March 2025 (Ringkjøbing Landbobank loan, December 2024). No later word that it runs.
Evidence and sources
- name: renewableenergymagazine.com/storage/nordic-solar-enters-battery-storage-mar…
- power: yahoo.com/news/company-makes-major-headway-first-10455240…
- status: greenpowerdenmark.dk/nyheder/batteripark-tager-form-batterier-er-gav…
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B023.