Being built, 20 MW · 60 MWh, in Slagelse Municipality, developed by BattMan Energy. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power20 MW
Capacity60 MWh
Duration3.0 hours
StatusBeing built, as of 25 October 2026
Bidding zoneDK2, East Denmark
MunicipalitySlagelse
Placed on the mapat Havrebjerg, the place its source names (GeoNames)
Nearest transmission stationHejninge (132 kV), 5 km away: 478 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026

Who is behind it

DeveloperBattMan Energy

Not published anywhere we have found: owner, ultimate owner, built by, optimiser.

What the sources say

Standalone. Known from BattMan Energy's project list only (read 25 October 2026).

Evidence and sources

From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B032.

All batteries  ·  On the map