Hoby solar park battery
Being built, 10 MW · 12 MWh, in Lolland Municipality, owned by Better Energy. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 10 MW |
| Capacity | 12 MWh |
| Duration | 1.2 hours |
| Status | Being built, as of 21 March 2024 |
| Owner’s date | end 2024, expected |
| Bidding zone | DK2, East Denmark |
| Municipality | Lolland |
| Grid connection | Beside the Hoby solar park on Lolland |
| Placed on the map | at Hoby, the place its source names (GeoNames) |
| Nearest transmission station | Gloslunde (132 kV), 2 km away: 199 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | Better Energy |
| Developer | Better Energy |
Not published anywhere we have found: ultimate owner, built by, optimiser.
What the sources say
Better Energy's first battery, expected by the end of 2024. No later word from Better Energy that it runs was found.
Evidence and sources
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B022.