Høegholm hybrid park battery

Being built, 60 MW · 120 MWh, in Syddjurs Municipality, owned by Høegholm Energipark ApS. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power60 MW
Capacity120 MWh
Duration2.0 hours
StatusBeing built, as of 28 April 2026
Owner’s dateQ4 2026, expected
Bidding zoneDK1, West Denmark
MunicipalitySyddjurs
Grid connectionCo-located with about 97 MW of solar
Placed on the mapat Tirstrup, the place its source names (GeoNames)
Nearest transmission stationMesballe (150 kV), 14 km away: 102 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026

Who is behind it

OwnerHøegholm Energipark ApS
Ultimate ownerGreenvolt Power
DeveloperGreenvolt Power
OptimiserReel

Not published anywhere we have found: built by.

What the sources say

Syddjurs Municipality's screening decision of 4 September 2025 (Høegholm, Tirstrup) is for up to 26 containers. The expected start moved from the first quarter of 2026 (October 2025) to the fourth quarter (April 2026).

Evidence and sources

From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B020.