Vitreous LabsEnergy transparency

Humlebæk battery

Operating, 10 MW · 27 MWh, in Fredensborg Municipality, developed by BattMan Energy. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power10 MW
Capacity27 MWh
Duration2.7 hours
StatusOperating, as of 25 October 2026
Bidding zoneDK2, East Denmark
MunicipalityFredensborg
Placed on the mapat Humlebæk, the place its source names (GeoNames)
Nearest transmission stationTeglstrupgård (132 kV), 8 km away: 323 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026

Who is behind it

DeveloperBattMan Energy

Not published anywhere we have found: owner, ultimate owner, built by, optimiser.

What the sources say

Standalone. Known only from BattMan Energy's project list (read 25 October 2026); owner and start date not published.

Evidence and sources

From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B017.

All batteries  ·  On the map