Hundested battery, Ullerup Skovvej
Announced, 18 MW, in Halsnæs Municipality, owned by Hundested BESS ApS. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 18 MW |
| Status | Announced, as of 3 September 2026 |
| Owner’s date | June 2027, expected |
| Bidding zone | DK2, East Denmark |
| Municipality | Halsnæs |
| Placed on the map | at Hundested, the place its source names (GeoNames) |
| Nearest transmission station | Valseværket (132 kV), 11 km away: 293 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | Hundested BESS ApS |
Not published anywhere we have found: ultimate owner, developer, built by, optimiser.
What the sources say
Screening decision of 3 September 2026: 18 MW storing for up to four hours, built from August 2026 to June 2027. The capacity this implies, 72 MWh, is not stated as a figure, so it is not entered.
Evidence and sources
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B059.