Kikkenborg wind turbine battery

Operating, 2.5 MW · 4.5 MWh, in Lemvig Municipality, owned by Lisby WP (Gunnar Lisby Kjær). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power2.5 MW
Capacity4.5 MWh
Duration1.8 hours
StatusOperating, as of 16 September 2026
Owner’s date16 September 2026, inaugurated
Bidding zoneDK1, West Denmark
MunicipalityLemvig
Address in the permitDamhusvej 49B, Lemvig
Grid connectionShares the cable and grid connection of one 3.3 MW Vestas V117 wind turbine; no new connection needed
Placed on the mapat the address its permit gives (Damhusvej 49B, Lemvig), found on OpenStreetMap
Nearest transmission stationIdomlund (150 kV), 15 km away: 580 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026

Who is behind it

OwnerLisby WP (Gunnar Lisby Kjær)
DeveloperBattMan Energy
OptimiserCentrica Energy

Not published anywhere we have found: ultimate owner, built by.

What the sources say

Two containers of LFP cells. Green Power Denmark reported the inauguration on 16 September 2026. Lemvig Municipality permitted BattMan a battery beside Gunnar Lisby Kjær's wind turbine at Damhusvej 49B on 12 February 2025, very likely this one.

Evidence and sources

From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B018.