Kolind solar park battery (NRGi)

Permitted, 4.6 MW, in Syddjurs Municipality, owned by NRGi Renewables. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power4.6 MW
StatusPermitted, as of 5 November 2025
Owner’s datesummer 2026, expected
Bidding zoneDK1, West Denmark
MunicipalitySyddjurs
Grid connectionBeside NRGi's solar park at Kolind, East Jutland's largest
Placed on the mapat Kolind, the place its source names (GeoNames)
Nearest transmission stationMesballe (150 kV), 5 km away: 102 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026

Who is behind it

OwnerNRGi Renewables
Ultimate ownerNRGi and Sampension
Built byCapture Energy (battery system)

Not published anywhere we have found: developer, optimiser.

What the sources say

Syddjurs Municipality approved it (release of 5 November 2025): 4.6 MW with about two hours' storage, "about 10 MWh", expected ready during summer 2026. No later word that it runs.

Evidence and sources

From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B045.