Kroghøj battery, Herning
Operating, 20 MW · 40 MWh, in Herning Municipality, owned by Jysk Energi, Endra and KP Invest Sol & Vind. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 20 MW |
| Capacity | 40 MWh |
| Duration | 2.0 hours |
| Status | Operating, as of 20 August 2026 |
| Owner’s date | August 2026, being put into operation |
| Bidding zone | DK1, West Denmark |
| Municipality | Herning |
| Placed on the map | at the centre of Herning Municipality (GeoNames) |
| Nearest transmission station | Herning Syd Vest (150 kV), 3 km away: 3 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | Jysk Energi, Endra and KP Invest Sol & Vind |
Not published anywhere we have found: ultimate owner, developer, built by, optimiser.
What the sources say
South of Herning. The trade site DOI reported on 20 August 2026 that the park is being put into operation (DOI only: no owner's release found).
Evidence and sources
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B019.