Kvosted Energy Park battery
Operating, 50 MW · 200 MWh, in Viborg Municipality, owned by Solar Park Kvosted ApS. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 50 MW |
| Capacity | 200 MWh |
| Duration | 4.0 hours |
| Status | Operating, as of 2 February 2026 |
| Owner’s date | 29 December 2025, actual |
| Bidding zone | DK1, West Denmark |
| Municipality | Viborg |
| Grid connection | Behind the meter of the Kvosted solar park (about 100 MWp, operating since 2022), sharing its grid connection |
| Placed on the map | at Kvosted, the place its source names (GeoNames) |
| Nearest transmission station | Loldrup (150 kV), 11 km away: 181 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | Solar Park Kvosted ApS |
| Ultimate owner | European Energy A/S |
| Developer | European Energy A/S |
| Built by | European Energy (own construction unit) |
| Optimiser | Danske Commodities |
What the sources say
Energised on 29 December 2025 and then in testing; inaugurated 2 February 2026. Built in seven months. The Nordic Investment Bank lent EUR 21.5m for it. Green Power Denmark (16 April 2026) says it delivers ancillary services to Energinet.
Evidence and sources
- name: dk.europeanenergy.com/2025/12/29/european-energy-saetter-stroem-til-n…
- municipality: danskecommodities.com/media/press/european-energy-and-danske-commodit…
- owner: nib.int/news/nib-finances-battery-storage-addition-to-s…
- status: dk.europeanenergy.com/2026/02/02/european-energy-indvier-nordeuropas-…
- grid connection: greenpowerdenmark.dk/nyheder/danmarks-stoerste-batteri-leverer-syste…
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B001.