Permitted, 40 MW, in Hedensted Municipality, owned by Solar Park Løsning ApS. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 40 MW |
| Status | Permitted, as of 7 January 2026 |
| Bidding zone | DK1, West Denmark |
| Municipality | Hedensted |
| Address in the permit | Ussingvej 29, Løsning |
| Placed on the map | at the address its permit gives (Ussingvej 29, Løsning), found on OpenStreetMap |
| Nearest transmission station | Hatting (150 kV), 4 km away: 16 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | Solar Park Løsning ApS |
| Ultimate owner | European Energy A/S |
Not published anywhere we have found: developer, built by, optimiser.
What the sources say
36 containers; screening and rural-zone permit 19 December 2025, revised 7 January 2026. The municipality's notice says European Energy applied.
Evidence and sources
- name: hedensted.dk/media/xnrcugfm/landzonetilladelse-og-dispensati…
- owner: backoffice.hedensted.dk/media/kxopxqmh/afgoerelse-om-at-ansoegt-batteri…
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B037.