Operating, 28 MW · 112 MWh, in Randers Municipality, owned by European Energy A/S. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power28 MW
Capacity112 MWh
Duration4.0 hours
StatusOperating, as of 14 July 2026
Owner’s dateJuly 2026, actual
Bidding zoneDK1, West Denmark
MunicipalityRanders
Address in the permitSøndergårdsvej 15, 8983 Gjerlev J
Grid connectionBeside the 88 MW Stouby solar park
Placed on the mapat the address its permit gives (Søndergårdsvej 15, 8983 Gjerlev J), found on OpenStreetMap
Nearest transmission stationHornbæk (150 kV), 15 km away: 128 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026

Who is behind it

OwnerEuropean Energy A/S
Ultimate ownerEuropean Energy A/S
DeveloperEuropean Energy A/S
OptimiserTwig (balance responsible party and optimiser)

Not published anywhere we have found: built by.

What the sources say

European Energy said on 14 July 2026 that Stouby and Agersted had both entered operation, without the day. Randers Municipality's rural-zone permit of 14 November 2025 was for 30 MW; the owner states 28 MW built.

Evidence and sources

From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B002.