Stouby hybrid park battery
Operating, 28 MW · 112 MWh, in Randers Municipality, owned by European Energy A/S. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 28 MW |
| Capacity | 112 MWh |
| Duration | 4.0 hours |
| Status | Operating, as of 14 July 2026 |
| Owner’s date | July 2026, actual |
| Bidding zone | DK1, West Denmark |
| Municipality | Randers |
| Address in the permit | Søndergårdsvej 15, 8983 Gjerlev J |
| Grid connection | Beside the 88 MW Stouby solar park |
| Placed on the map | at the address its permit gives (Søndergårdsvej 15, 8983 Gjerlev J), found on OpenStreetMap |
| Nearest transmission station | Hornbæk (150 kV), 15 km away: 128 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | European Energy A/S |
| Ultimate owner | European Energy A/S |
| Developer | European Energy A/S |
| Optimiser | Twig (balance responsible party and optimiser) |
Not published anywhere we have found: built by.
What the sources say
European Energy said on 14 July 2026 that Stouby and Agersted had both entered operation, without the day. Randers Municipality's rural-zone permit of 14 November 2025 was for 30 MW; the owner states 28 MW built.
Evidence and sources
- name: europeanenergy.com/2026/07/14/european-energy-grid-connects-two-ba…
- municipality: randers.dk/media/da4lpll2/landzonetilladelse-soendergaards…
- developer: europeanenergy.com/2026/04/08/european-energy-partners-with-twig-f…
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B002.