Vandel III battery
Operating, 60 MW · 120 MWh, in Vejle Municipality, owned by Infranode and Bregentved Gods. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 60 MW |
| Capacity | 120 MWh |
| Duration | 2.0 hours |
| Status | Operating, as of 25 September 2026 |
| Owner’s date | 25 September 2026, actual |
| Bidding zone | DK1, West Denmark |
| Municipality | Vejle |
| Grid connection | Shares the grid connection of the 162 MWp Vandel III solar park, Erhvervspark Vandel |
| Placed on the map | at Vandel, the place its source names (GeoNames) |
| Nearest transmission station | Mørup (150 kV), 4 km away: · MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | Infranode and Bregentved Gods |
| Ultimate owner | Infranode |
| Developer | Infranode |
Not published anywhere we have found: built by, optimiser.
What the sources say
Six 10 MW units, expandable to 240 MWh. Investment decision January 2026; inaugurated 25 September 2026, the date used as its start. The split of ownership between Infranode and Bregentved Gods is not stated; supplier and optimiser are not named.
Evidence and sources
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B006.