A battery installation in Madrid, Madrid, environmental decision. Every fact below is taken from the latest act in the regional gazette of Madrid that states it, and every act is linked.

In the gazette

Battery powernot stated in any act
PromoterIguña FV, S. L.
ConfigurationStand-alone
MunicipalityMadrid
ProvinceMadrid
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
2 Jul 2026Environmental decisionCONSEJERÍA DE MEDIO AMBIENTE, AGRICULTURA E INTERIORBOCM-20260702-49

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Madrid, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.

All installations  ·  On the map